Notice to Residents - Construction Schedule for Improvements to Palm Avenue (From Stirling Road to Griffin Road) - Broward County Project No. 5322 

Please be advised that Broward County will be issuing Notice to Proceed (NTP) to the contractor to commence construction activities during the week of May 21, 2012 for the improvements of Palm Avenue between Griffin Road and Stirling Road. The project is scheduled to be completed within 19 months. 

The Palm Avenue project will widen the corridor from a two (2) to a four 4-lane divided roadway between Stirling Road and Griffin Road. The improvements include the construction of curb/ gutter, sidewalks, traffic separators, drainage, signalization, illumination system, landscape, irrigation, pavement markings, and water utilities.

The prime contractor for this project is Southeastern Engineering Contractors, Inc. and the field office for the contractor and inspection team is at: 

The Centre at Stirling and Palm 
9900 Stirling Road, Suite 200A
Cooper City, FL 33024

For any comments or questions that you may have during the construction time of Palm Avenue, please contact the following staff from Broward County Highway Construction & Engineering Division: 

Bryan Williams, P.E., Project Manager IV
Construction Engineering Inspection Section
E-mail: bwilliams@broward.org

Telephone: (954) 577-4562

Julio Gurrea, Project Manager II
Construction Management Section
E-mail: jgurrea@broward.org

Telephone: (954) 577-4599



Best regards,
Commissioner John Sims

Cooper City, FL
954-445-6997

No comments:

Post a Comment

Thanks for posting your concerns and leaving your comment! it may be approved shortly...

Note: Only a member of this blog may post a comment.